Ready-mix concrete saves time, but you still need to check what arrives at your site.
Check the delivery challan
- Grade of concrete (for example M20 or M25) matches what was ordered
- Time of batching — concrete should be placed well within its working time
- Quantity delivered
Slump test
The slump test shows how workable the concrete is. Too dry and it won't compact properly; too wet and it loses strength. Your engineer compares the result with the specified range.
Never allow
- Adding extra water at site to make pouring easier
- Pouring concrete that has been waiting too long
Video: CivilEngineerwork07 on YouTube.