Blocks to order

183 nos

174 blocks + 5% wastage · wall area 15.00 m²

Mortar

Wet mortar
0.213 m³ (7.51 cft)
Cement
1.16 bags (58 kg)
Sand
0.242 m³ (8.56 cft)

Estimates for planning. Confirm final quantities from drawings with an engineer.

How it's calculated

  1. Blocks = wall face area ÷ ((block length + joint) × (block height + joint)).
  2. Wet mortar = wall volume − blocks × block volume; dry mortar = wet × 1.33.
  3. Cement and sand split by the mortar ratio.

Good to know

AAC blocks are usually laid with thin-bed adhesive (2–3 mm) instead of 10 mm mortar. Set the joint to 3 mm and ignore the cement/sand lines in that case, and follow the adhesive maker's coverage.